FAA air traffic control modernization has two main eras: the long-running NextGen program and the accelerated Brand New Air Traffic Control System (BNATCS/“Modern Skies”) effort launched in 2025.NextGen (roughly 2003–2025)
  • 2003–2004: Vision 100 Act creates the Joint Planning and Development Office; DOT releases the Integrated Plan for the Next Generation Air Transportation System. 
  • 2007–2010s: Concept of Operations; early Performance-Based Navigation routes; ADS-B ground infrastructure largely complete by ~2014; En Route Automation Modernization (ERAM) fully deployed at all 20 en-route centers by 2015; Data Comm tower services finished at planned airports by 2016. 
  • 2019–2020: ADS-B becomes operational nationwide (ahead of the 2020 equipage mandate); further Data Comm and information-sharing advances via SWIM. 
  • 2021: Nationwide Standard Terminal Automation Replacement System (STARS) rollout complete, replacing older terminal radar systems and incorporating ADS-B. 
  • 2024–2025: Data Comm en-route services reach continuous operation across all 20 Air Route Traffic Control Centers. The NextGen office closes at the end of 2025 under the FAA Reauthorization Act of 2024, with responsibilities shifting to a new modernization office. ADS-B and related systems are described as mature in most controlled airspace. 
NextGen improved navigation, surveillance, and digital communications but faced delays, mixed milestone achievement, and criticism that only a modest share of projected benefits had been realized by the mid-2020s. Core legacy infrastructure (especially telecommunications) remained largely intact. Brand New Air Traffic Control System / Modern Skies (2025–present)
  • May 2025: Initiative launched to replace outdated radar, software, hardware, and telecommunications on an accelerated schedule, distinct from (but building on) NextGen. 
  • July 2025: Congress appropriates $12.5 billion (via the One Big Beautiful Bill Act) primarily for Phase 1 systems modernization. 
  • Late 2025: Peraton selected as prime integrator; workstreams organized around communications (copper-to-fiber and IP), surveillance (new radars), automation (electronic flight strips / TFDM), facilities, Alaska-specific systems, and training. 
  • Target: Phase 1 complete by December 2028. This pulls forward multiple prior schedules (e.g., voice radio replacements by roughly nine years). Goals include ~5,170 new high-speed connections, ~27,000+ new radios, 450 digital voice switches, 612 new radars, electronic flight strips at 89 airports, and related upgrades across ~4,600 sites. 
  • Progress as of mid-November 2026 (FAA Modern Skies data): ~71% of telecommunications replaced (3,651 of 5,170), ~51% of IP voice switches installed, ~31% of radio sites converted and electronic flight strips implemented, with radar deployment still early (~3%). Copper-to-fiber work on the legacy FAA Telecommunications Infrastructure (FTI) network (handled by L3Harris and partners) was already well advanced and was the context for the November 13, 2026 nationwide ground stop. 
Phase 2 (deeper automation and traffic optimization) has later or still-developing timelines and higher cost estimates. GAO reviews have noted the ambitious speed of BNATCS and called for stronger cost and schedule planning. The November 2026 outage occurred during ongoing sustainment/upgrade work on aging copper-based systems that the 2025–2028 effort is intended to fully replace. Official FAA pages (faa.gov/nextgen and faa.gov/new-atcs) are the primary sources for program status.